CIS invoice finance or retention release: which one fixes your cash gap?

They fund different money, so the first job is to name which money you are short of. Invoice finance built for CIS subcontractors advances against the cash a contractor will pay on a live, undisputed application, after the CIS deduction and the retention have come off. Retention release finance is a separate product for the retention itself, which is held back until a release condition is met and which the standard invoice finance terms we read leave out. Neither can touch the CIS deduction: it goes to HMRC, and the fix for it is on the tax side. Most subcontractors carrying several jobs have all three gaps at once.

General information, not legal or tax advice. Figures are from GOV.UK, legislation.gov.uk, Parliament, two published funder contracts and the government's payment practices register, each linked where it is used.

CIS invoice finance advances against the net cash a contractor will pay on a live, undisputed application or invoice, after the CIS deduction (20% registered and verified, 30% otherwise, 0% with gross payment status, labour only) and after retention. Retention release finance is a separate specialist product for retention money held until a release condition is met; standard invoice finance terms such as Barclays' CID terms (retention monies ineligible for bad debt cover) and Aldermore's (retentions as Dilutions) leave it out. The CIS deduction cannot be financed because it is paid to HMRC; a limited company offsets it through its Employer Payment Summary and a sole trader through Self Assessment, and gross payment status stops it. More detail and scope

This page covers:

which funding route fits which construction cash gap: live applications, CIS deductions, retentions inside and past their release date, disputed and pay-when-paid sums.

Not covered here:

Retention release finance providers in detail (see Retention Release Finance), financing CIS payroll (see CIS Payroll Finance), the adjudication process (see Adjudication for an Unpaid Application for Payment), tax advice on CIS.

One application, three pieces of money

A CIS subcontractor's application for payment does not arrive as one sum. The payer holds back a retention under the contract. The contractor then deducts CIS from the labour part of what it pays and sends that to HMRC. What is left lands in your account on the final date for payment. Each piece has a different owner in the meantime and a different release date, which is why no single facility covers all three.

The decision tree

Take one sum you are waiting for and start at question 1. If you have several gaps, run each one through separately.

  1. 1. Is the money you are short of held back as retention?

    That is, the contract lets the payer keep it until something happens: completion, the end of the defects period, a certificate.

    Yes: go to question 2. No: go to question 3.

  2. 2. Has the release condition been met and the release date passed?

    Yes, and it is still unpaid: outcome A. No, it is still inside its release period: outcome B.

  3. 3. Is the gap the CIS deduction itself?

    You were paid, but 20% or 30% of the labour part went to HMRC and you are waiting to use it against your tax.

    Yes: outcome C. No: go to question 4.

  4. 4. Is the sum applied for or invoiced, undisputed, and on terms that do not wait for someone else to pay?

    Yes: outcome D. No, it is disputed or on pay-when-paid terms: outcome E.

A. Retention past its release date: chase it as a due sum

Once the condition is met, released retention is a payment due under the contract like any other, with its own due date and final date for payment. The problem is non-payment, not timing, so a finance product is not the first fix. Check the payer has not served a valid pay less notice, then chase it, and if it is disputed, consider adjudication. The adjudication vs invoice finance guide covers that choice.

B. Retention still held: retention release finance, or plan around the wait

This is the only case retention release finance exists for. Standard invoice finance will not reach it (the contract terms are below), so either a specialist advances against it or you carry it in your cash flow until release. See retentions release finance for how the product works. Ask any funder for its advance rate and fee in writing: the two funder contracts we read publish neither for retentions.

Before you pay to accelerate it, read the release clause. If it waits for something under the main contract, such as the main contract's defects certificate, section 110(1A) of the Construction Act says a contract making payment conditional on obligations under another contract, or on someone's decision that they have been performed, does not have an adequate payment mechanism (with a narrow exception in s110(1C)). The Scheme for Construction Contracts then fills the gap, which can bring the payment date forward. Take legal advice on your wording.

C. The CIS deduction: fix it with HMRC, not a funder

No funder can advance money that goes to HMRC. GOV.UK treats deductions as advance payments towards your own tax and National Insurance, and how you get the benefit depends on how you trade:

  • Limited company: enter the year-to-date deductions on the Employer Payment Summary alongside the Full Payment Submission, and HMRC takes them off what the company owes through payroll. Anything left carries forward within the tax year and can be reclaimed after it ends. GOV.UK warns against using the Corporation Tax return for this.
  • Sole trader or partner: the deductions go on the Self Assessment return at the end of the tax year, so the cash can be tied up for months.
  • Paying 30%: the higher rate applies if you are not registered or the contractor cannot verify you. Give each contractor the exact details you registered with, including your UTR.
  • Stopping deductions: gross payment status, if you pass the tests in the FAQ below. It is reviewed every year.

If what you need is cash to meet your own CIS payroll rather than recover deductions, that is a different product: see CIS payroll finance.

D. A live, undisputed sum: CIS-aware invoice or construction finance

This is what invoice finance is for. A construction facility funds against applications for payment as well as invoices; Aldermore's conditions define the Invoice Value as the gross amount "according to the invoice or application for payment". The base a funder can safely lend against is the net cash the contractor will actually pay, after retention and CIS, and the calculator below works that out. See application for payment finance and subcontractor finance, and use the CIS invoice template so the labour, materials and deduction lines are clear to both payer and funder.

E. Disputed or pay-when-paid: resolve the payment right first

Funders will not advance against these. Aldermore's construction conditions designate debts under contracts with "pay when paid" or "pay when certified" terms, and debts in dispute or referred to adjudication, as Disapproved. The law is on your side for the first: section 113 makes a clause conditioning payment on the payer being paid by someone else ineffective, unless that third party is insolvent. For disputes, adjudication gives a decision that then becomes a fundable debt.

Which fix fits which construction cash gap
The money you are short ofRouteWhyCheck first
Retention still inside its release periodRetention release finance, or waitStandard invoice finance terms we read exclude or reserve against itCheck whether release depends on the main contract (s110(1A))
Retention past its release date and unpaidChase it as a due sum, adjudicate if disputedA finance product is not the first fixYour notices and the final date for payment
The CIS deduction itself (20% or 30%)HMRC: offset, reclaim, or gross payment statusNo funder can advance money that goes to HMRCVerification, registration, the GPS tests
A live, undisputed application or invoiceCIS-aware invoice or construction financeFunds the net cash the contractor will payPay-when-paid, assignment bans, disputes
A disputed or pay-when-paid sumAdjudication, or rely on s113Funders designate these debts as not fundablePay less notice, the Scheme

Source: Market Invoice, from the GOV.UK CIS guidance, HGCRA 1996 and the Aldermore and Barclays published terms cited on this page

A summary of the decision tree above. It is general information, not legal or tax advice.

View as plain-text Markdown
### Which fix fits which construction cash gap

| The money you are short of | Route | Why | Check first |
| --- | --- | --- | --- |
| Retention still inside its release period | Retention release finance, or wait | Standard invoice finance terms we read exclude or reserve against it | Check whether release depends on the main contract (s110(1A)) |
| Retention past its release date and unpaid | Chase it as a due sum, adjudicate if disputed | A finance product is not the first fix | Your notices and the final date for payment |
| The CIS deduction itself (20% or 30%) | HMRC: offset, reclaim, or gross payment status | No funder can advance money that goes to HMRC | Verification, registration, the GPS tests |
| A live, undisputed application or invoice | CIS-aware invoice or construction finance | Funds the net cash the contractor will pay | Pay-when-paid, assignment bans, disputes |
| A disputed or pay-when-paid sum | Adjudication, or rely on s113 | Funders designate these debts as not fundable | Pay less notice, the Scheme |

Source: Market Invoice, from the GOV.UK CIS guidance, HGCRA 1996 and the Aldermore and Barclays published terms cited on this page

A summary of the decision tree above. It is general information, not legal or tax advice.

What two published funder contracts say

Most funders do not publish their terms. These two do, and they show how retentions and CIS are handled in the documents you would sign.

Two things follow. Retentions sit outside the funded amount, which is why a separate product exists for them. And a CIS change is a facility event: a lapse in gross payment status can end the facility, not just cost you 20%. Read the equivalent clauses in your own agreement. Profiles: Aldermore, Barclays.

Split your own application

Enter one application or invoice. The calculator shows how much reaches you now, how much is held as retention, how much goes to HMRC, and what an advance on the net cash would be at the rate your funder quotes. It runs in your browser. We note the figures you enter and the result, so we can see whether the tool helps; this is never linked to an enquiry (see our privacy policy).

Piece of the application Amount
Cash the contractor pays you now£33,440
Advance on that cash at your funder's rate£26,752
CIS deducted now (to HMRC)£4,560
Retention held back£2,000
Retention cash at release, after its CIS£1,760
Total CIS on the whole application£4,800

Labour is treated as an even share of every pound billed, retention included. CIS is deducted when a payment is made, so the labour part of the retention is deducted when the retention is paid. The advance rate field starts at a placeholder, not a market figure: enter the rate in your facility letter. Funders set their own base and reserves; this uses the net cash you will be paid as the cautious base.

Worked example

The application below is invented to show the split. The 5% retention is the rate large companies most often gave in the payment practices data further down; the 80% advance is a placeholder, not a view on what funders offer.

Worked example: the application
InputExample figure
Application for payment, before retention and CIS (no VAT: reverse charge)£40,000
Labour share of the work60%
Retention under the subcontract5%
CIS deduction rate (registered and verified)20%
Advance rate your funder quotes (placeholder, not a market figure)80%

Invented figures, except the 5% retention, which is the most common standard rate in the payment practices data on this page. CIS rates from GOV.UK.

View as plain-text Markdown
### Worked example: the application

| Input | Example figure |
| --- | --- |
| Application for payment, before retention and CIS (no VAT: reverse charge) | £40,000 |
| Labour share of the work | 60% |
| Retention under the subcontract | 5% |
| CIS deduction rate (registered and verified) | 20% |
| Advance rate your funder quotes (placeholder, not a market figure) | 80% |

Invented figures, except the 5% retention, which is the most common standard rate in the payment practices data on this page. CIS rates from GOV.UK.
Worked example: £40,000 application split into cash now, CIS and retention
PieceHow it is worked outAmountWhen it reaches you
Retention held back£40,000 x 5%£2,000At the release date, if the condition is met
Payable now£40,000 minus retention£38,000On the final date for payment
CIS deducted from the payment now£38,000 x 60% labour x 20%£4,560Offset or reclaimed through HMRC, not the contractor
Cash the contractor pays you nowPayable now minus CIS£33,440On the final date for payment
Advance against that cash£33,440 x 80%£26,752When the funder approves the debt
CIS deducted when the retention is paid£2,000 x 60% x 20%£240Through HMRC, in the tax year it is paid
Retention cash when releasedRetention minus its CIS£1,760At release

Source: Market Invoice, applying the GOV.UK CIS deduction rules to the example figures

Of the £40,000 applied for, £33,440 is paid now, £4,800 goes to HMRC in total and £1,760 arrives only at release.

View as plain-text Markdown
### Worked example: £40,000 application split into cash now, CIS and retention

| Piece | How it is worked out | Amount | When it reaches you |
| --- | --- | --- | --- |
| Retention held back | £40,000 x 5% | £2,000 | At the release date, if the condition is met |
| Payable now | £40,000 minus retention | £38,000 | On the final date for payment |
| CIS deducted from the payment now | £38,000 x 60% labour x 20% | £4,560 | Offset or reclaimed through HMRC, not the contractor |
| Cash the contractor pays you now | Payable now minus CIS | £33,440 | On the final date for payment |
| Advance against that cash | £33,440 x 80% | £26,752 | When the funder approves the debt |
| CIS deducted when the retention is paid | £2,000 x 60% x 20% | £240 | Through HMRC, in the tax year it is paid |
| Retention cash when released | Retention minus its CIS | £1,760 | At release |

Source: Market Invoice, applying the GOV.UK CIS deduction rules to the example figures

Of the £40,000 applied for, £33,440 is paid now, £4,800 goes to HMRC in total and £1,760 arrives only at release.

Invoice finance can speed up the £33,440. It cannot touch the £4,560 of CIS, which only HMRC gives back, or the £2,000 retention, which only a retention release product or the release date can unlock. On one application those last two look small, but they build up across every open job, and that total is the figure to put to a funder or to HMRC.

How large companies use retentions: the payment practices data

Since the Reporting on Payment Practices and Performance (Amendment) Regulations 2025, large companies that report their payment practices also answer questions on retention in their construction contracts. We took the government's full export, kept the reports that say the company had qualifying construction contracts, and used each company's latest report. Those reports were filed from 23 October 2025 to 23 September 2026.

Retention clauses in large companies' construction contracts: 792 of 1,454 companies use them
Answer in the latest reportCompaniesShare
Companies whose latest report says they had qualifying construction contracts1,454
Of those, companies that use retention clauses79254%
Retention in all of their construction contracts20726% of users
Retention used in specific circumstances50964% of users
Retention held at a standard rate41552% of users
Release is staged (for example part at completion, part after the defects period)60476% of users
Terms match what their own client holds from them (parity)30138% of users
Release answer names the main, head or principal contract17Keyword floor, see note

Source: Department for Business and Trade payment practices export (Open Government Licence v3.0), latest report per company, analysed by Market Invoice

Counts are of companies, not contracts, and are the companies' own answers. The main, head or principal contract count is a keyword search of the free-text release answers, so it is a floor: companies can tie release to the main contract without using those words. Built by scripts/assets/build-ppr-retentions.py on 24 September 2026.

View as plain-text Markdown
### Retention clauses in large companies' construction contracts: 792 of 1,454 companies use them

| Answer in the latest report | Companies | Share |
| --- | --- | --- |
| Companies whose latest report says they had qualifying construction contracts | 1,454 |  |
| Of those, companies that use retention clauses | 792 | 54% |
| Retention in all of their construction contracts | 207 | 26% of users |
| Retention used in specific circumstances | 509 | 64% of users |
| Retention held at a standard rate | 415 | 52% of users |
| Release is staged (for example part at completion, part after the defects period) | 604 | 76% of users |
| Terms match what their own client holds from them (parity) | 301 | 38% of users |
| Release answer names the main, head or principal contract | 17 | Keyword floor, see note |

Source: Department for Business and Trade payment practices export (Open Government Licence v3.0), latest report per company, analysed by Market Invoice (https://check-payment-practices.service.gov.uk/export/csv/)

Counts are of companies, not contracts, and are the companies' own answers. The main, head or principal contract count is a keyword search of the free-text release answers, so it is a floor: companies can tie release to the main contract without using those words. Built by scripts/assets/build-ppr-retentions.py on 24 September 2026.
Standard retention rates given by 415 large companies: 5% is the most common
Standard rateCompaniesShare of those giving a rate
5%26764%
3%12129%
2%154%
10%92%
4%20%
15%10%
View as plain-text Markdown
### Standard retention rates given by 415 large companies: 5% is the most common

| Standard rate | Companies | Share of those giving a rate |
| --- | --- | --- |
| 5% | 267 | 64% |
| 3% | 121 | 29% |
| 2% | 15 | 4% |
| 10% | 9 | 2% |
| 4% | 2 | 0% |
| 15% | 1 | 0% |

Source: Department for Business and Trade payment practices export, analysed by Market Invoice (https://check-payment-practices.service.gov.uk/export/csv/)

So about half of large companies with construction contracts use retentions (54%), most of them only in some contracts, and the rates cluster at 5% and 3%. Asked for the value of retentions held compared with their total payments, the 791 companies that answered gave a median of 2%, with a quarter at 0% and a quarter at 4% or more. Release is staged for 76% of users, so most retentions come back in two parts.

Two limits. These are large companies, which pay many subcontractors but are not the whole market. And the answers describe policy, not what happened on a given job. Your own subcontract is the source for your rate and release terms. For payment times in the sector, see UK construction late payment statistics.

What the retention ban would change

The government's response to its late payment consultation said it proposed "a legislative measure to prohibit the deduction and withholding of retention payments under the terms of a construction contract", and that it would consult further before taking a final decision on implementation. The Commercial Payments Bill carries that ban. It passed third reading in the House of Lords on 20 October 2026 and had its first reading in the House of Commons on 21 October 2026, so it is not law (stage checked 15 November 2026). In the version as amended on Report in the Lords, printed 15 September 2026, it would add new sections to the Construction Act:

For this decision, that means retention release finance is a product for retentions already held and for contracts signed before the ban bites, not a long-term fixture. It does nothing to CIS or to the case for invoice finance on live applications. The bill can still change; the regulatory timeline tracks it.

Before you speak to a funder

  1. List every open job with its application value, retention held, release condition and release date.
  2. Total the CIS deducted this tax year from your payment and deduction statements, which contractors must give you within 14 days of the end of each tax month.
  3. Check whether you would pass the gross payment status tests, and when HMRC next reviews you if you hold it.
  4. Read each subcontract for pay-when-paid wording, assignment bans and release clauses that wait on the main contract.
  5. Ask each funder in writing how it treats retentions, CIS deductions, applications for payment and a change in CIS status.

For the funders that name construction as a sector, see our best invoice finance for construction picks and the construction finance hub.

Limits of this page

Two published funder contracts are not a market survey, and a funder can agree different terms with you. The calculator treats labour as an even share of the application and does not model reserves, fees or discount charges. The Construction Act rules quoted apply in England, Wales and Scotland; Northern Ireland has its own Order. CIS rules are as GOV.UK states them today, and the retention ban is a bill. Check your own contracts, and take tax or legal advice where the sums matter.

AP

Adam Parker

Founder & Managing Director, Muswell Rose, founder and PSC of Best Business Loans Ltd

Adam was managing director of Penny, a UK invoice finance business, from July 2020 to November 2023. His career runs through insurance, mortgages, commercial finance and fintech lending. He writes the Market Invoice library. Career record.

AI-assisted check

Get Free Invoice Finance Quotes

Tell us about your applications, retentions and CIS status. We pass your details to one or more of the finance partners we work with, who come back to you with quotes. Free, no obligation.

Step 1 of 3 · Your business

Start typing and we'll search Companies House.

Free to you. We may be paid by the finance partners we introduce you to. This could be a fee or commission, depending on the partner and the finance arranged. It does not change what you pay. See our privacy policy.

Free · No obligation · Nothing to pay us

How we make money: Market Invoice is an independent comparison service, not a lender. We may be paid by the finance partners we introduce you to. This could be a fee or commission, depending on the partner and the finance arranged. It does not change what you pay. How we are funded.

CIS Invoice Finance vs Retention Release FAQ

Can invoice finance fund construction retentions?

Not usually on standard terms. Barclays' published Confidential Invoice Discounting Standard Terms list "Debts that relate to retention monies" among the debts that are ineligible for its bad debt protection cover, and have the customer warrant that each debtor will pay "without retention, set-off or deduction".

Aldermore's construction finance conditions accept that the customer may deduct a retention, and treat retentions as Dilutions that reduce the value of a debt. In both cases the retained sum sits outside what is funded. Retention release finance is a separate, specialist product aimed at money that is held back until a release condition is met.

Can I get finance against my CIS deductions?

No. The deduction is paid by the contractor to HMRC, so it never reaches you or the funder. GOV.UK treats it as an advance payment towards your own tax and National Insurance. A limited company recovers it through its payroll scheme by entering the deductions on its Employer Payment Summary, which HMRC takes off what the company owes; a sole trader or partner recovers it through the Self Assessment return. The only way to stop deductions being taken is gross payment status.

What CIS deduction rate applies to my invoices?

GOV.UK says 20% if you are registered for CIS and the contractor can verify you, 30% if either is not true, and none if you have gross payment status. The deduction is taken only from the labour part: not from VAT, materials you paid for, plant hired for the job, consumable stores or manufacturing and prefabricating materials.

What do I need for gross payment status?

GOV.UK lists three business tests (tax and National Insurance paid on time in the past, construction work in the UK, a business bank account) and a turnover test on the last 12 months, ignoring VAT and materials: at least £30,000 for a sole trader; £30,000 for each partner or £100,000 for the whole partnership; £30,000 for each director or £100,000 for the whole company, and £30,000 for each of them if the company is controlled by 5 people or fewer. HMRC reviews the status every year and, if it cancels it, you wait a year before reapplying.

Does losing gross payment status affect my invoice finance facility?

It can. In Aldermore's published Construction Finance Conditions, the suspension or cancellation of your CIS registration for gross payment, or for payment under deduction, is a Termination Event, and you must tell the funder immediately about any change to your CIS registration. The same conditions say a refund of CIS tax deducted from a funded debt counts as a Remittance that you must pass to the funder. Read your own agreement for the equivalent clauses.

Is a retention clause that waits for the main contract's defects certificate enforceable?

It may not be a valid payment mechanism. Section 110(1A) of the Housing Grants, Construction and Regeneration Act 1996, in force since 1 October 2011 in England and Wales and 1 November 2011 in Scotland, says a contract fails the adequate payment mechanism requirement where it makes payment conditional on the performance of obligations under another contract, or on a decision by any person as to whether they have been performed.

Section 110(1C) carves out a narrow case. Where the mechanism fails, the Scheme for Construction Contracts fills the gap. Whether it catches your clause is a question for a construction solicitor.

Are retentions being banned?

Not yet. The Commercial Payments Bill would ban retention clauses in construction contracts. It completed its House of Lords stages on 20 October 2026 and had its first reading in the House of Commons on 21 October 2026 (stage checked 15 November 2026). In the version as amended on Report in the Lords (15 September 2026), a two-year transition period starts when the retention sections are brought into force by regulations; clauses agreed during it stop working three years after that date, and clauses agreed after the transition are void. It is still a bill and can change before it becomes law.